Electromagnetic Compatibility Measures for Bus Adapter 170 INT 110 03
44
Central Shielding Measures for the INTERBUS
Central shielding
measures
For the commissioning phase, a large surface area connection should be made
between each cable shield and ground (FE/PE rail) directly after the cable enters the
switch cabinet.
Static discharge Very long bus cables, which have been laid but not yet connected, are discharged
as follows:
Notes for
connection the
cable shield with
earth
Step Action
1 Begin with the static discharge with the INTERBUS plug nearest to the FE/PE
rail.
2 Touch the FE/PE rail of the switch cabinet with the metal of the plug case.
3 Then plug the bus plug into the device, but only after this has been statically
discharged.
4 Discharge the cable’s other INTERBUS plugs in the same way and then plug
these into the device.
Note: The metal guide of the INTERBUS plug is internally connected with the cable
shield during the construction of the cable. If the bus cable plug is plugged into the
module’s INTERBUS interface, a short connection is automatically established
between the shield and PE.